Deposit |
Paid at signing of the Contract between Austart Homes and the Client. |
5% |
1st Progress |
Completion of floor slab. (Base) |
15% |
2nd Progress |
Completion of external block work & roof trusses. (Block and Trusses) |
20% |
3rd Progress |
Completion of lock-up (roof on, external wall cladding, windows & doors but excludes garage panelift door) (Enclosed) |
25% |
4th Progress |
Completion of Pre-Paint stage (excludes plumbing and electrical fit-off and painting) (Fixing) |
20% |
5th Final |
Upon Practical Completion Certificate & Prior to Handover |
Balance or 15% |